Here is a quick update regarding the Bridge placement in Palmer Lake. We’re very close! The Railroad is a bit difficult to deal with, but we just have to roll with it.  We will try to keep rolling updates here as we get them.

Published Wednesday Dec 11 10:16am
We thought we would be placing the bridge on Thursday the 12th, but the railroad is requesting a last minute “pre-pickup and place” conference, we hope to have that this Friday the 13th in the afternoon.  It’s a small set back, and a prudent one considering we’re lifting a giant bridge over an active railroad track.

The huge crane should mobilize to the site next Wednesday the 18th. The schedule is to pick up and place the bridge Thursday the 19th.

The bright side is we have a target date – Thursday, Dec. 19.

We thought we would be placing the bridge on Thursday the 12th, bu

We will do our best to keep you updated here.